Kostas,

We keep a little table called Holiday, with the correct dates for all
holidays, including those dreadful floating ones.  Then before you count
days, you query that table for how many are between your first date and
your last date and you're all set.  You could include weekend days in
the table if you liked.

HTH,

 
 
Liz 
 
 
Liz Doering 
elizabeth.j.doering at wellsfargo.com 
612.667.2447 
 
This message may contain confidential and/or privileged information. If
you are not the addressee or authorized to receive this for the
addressee, you must not use, copy, disclose, or take any action based on
this message or any information herein. If you have received this
message in error, please advise the sender immediately by reply e-mail
and delete this message. Thank you for your cooperation.



-----Original Message-----
From: accessd-bounces at databaseadvisors.com
[mailto:accessd-bounces at databaseadvisors.com] On Behalf Of Kostas
Konstantinidis
Sent: Thursday, November 15, 2007 3:39 PM
To: Access Developers discussion and problem solving
Subject: Re: [AccessD] MSAccess 2007 - Count days

Jim,
Excellent work but what I need to know is how many working days there
are between two dates, so I will be able to count at all times the paid
holydays of my fulltime employees

thank's a lot
/kostas




----- Original Message -----
From: "Hale, Jim" <Jim.Hale at fleetpride.com>
To: "Access Developers discussion and problem solving" 
<accessd at databaseadvisors.com>
Sent: Thursday, November 15, 2007 10:33 PM
Subject: Re: [AccessD] MSAccess 2007 - Count days


>
> I am sending you a database offline
> Regards,
> Jim Hale
>
> -----Original Message-----
> From: accessd-bounces at databaseadvisors.com
> [mailto:accessd-bounces at databaseadvisors.com] On Behalf Of Kostas
> Konstantinidis
> Sent: Thursday, November 15, 2007 1:50 PM
> To: Access Developers discussion and problem solving
> Subject: [AccessD] MSAccess 2007 - Count days
>
> Hi all,
>
> Does anybody know how it could be possible to count
> the work days between two days excluding weekends and local holidays
> To my coutry there are several dates as holidays and some of them
> are moving year by year
>
> many thank's to all
>
> /kostas
> -- 
> AccessD mailing list
> AccessD at databaseadvisors.com
> http://databaseadvisors.com/mailman/listinfo/accessd
> Website: http://www.databaseadvisors.com
>
>
***********************************************************************
> The information transmitted is intended solely for the individual or
> entity to which it is addressed and may contain confidential and/or
> privileged material. Any review, retransmission, dissemination or
> other use of or taking action in reliance upon this information by
> persons or entities other than the intended recipient is prohibited.
> If you have received this email in error please contact the sender and
> delete the material from any computer. As a recipient of this email,
> you are responsible for screening its contents and the contents of any
> attachments for the presence of viruses. No liability is accepted for
> any damages caused by any virus transmitted by this email.
>
> -- 
> AccessD mailing list
> AccessD at databaseadvisors.com
> http://databaseadvisors.com/mailman/listinfo/accessd
> Website: http://www.databaseadvisors.com
> 

-- 
AccessD mailing list
AccessD at databaseadvisors.com
http://databaseadvisors.com/mailman/listinfo/accessd
Website: http://www.databaseadvisors.com





More information about the AccessD mailing list