Wortz, Charles
CWortz at tea.state.tx.us
Mon Jul 14 11:03:18 CDT 2003
John, Are you saying you cannot do that in M$Project? I don't fool around that much with M$Project these days, but IIRC you can list tasks by the resources assigned. Similar tasks would have similar resources assigned if you group resources. You haven't said which version of M$Poject you are using, but in P2K and above there are hundreds of ways of slicing and dicing the data. Charles Wortz Software Development Division Texas Education Agency 1701 N. Congress Ave Austin, TX 78701-1494 512-463-9493 CWortz at tea.state.tx.us -----Original Message----- From: JOHNWARDBELL at aol.com [mailto:JOHNWARDBELL at aol.com] Sent: Monday 2003 Jul 14 10:18 To: accessd at databaseadvisors.com Subject: Re: [AccessD] MSProject to Access Charles I am trying to pick the same task that appears in each and every project and list them with start and finish date, task duration and resource.