Hadyn Morgan
hadyn at dataconcepts.co.nz
Tue Sep 30 21:22:21 CDT 2003
When do you say a project has started? I have a client that has said 'Yes' to a project, but has not signed off the spec, or the quote, and now wants to negotiate penalty clauses before they sign (if we don't deliver on time to the proposed end date (11 weeks from start of project) they reduce total payment by 8% for each full week we are late). I have managed to get them to exclude Acts of God etc, and have suggested that if they are to blame for the delay we should be allowed to charge them for the extra time. Any thoughts? Kind regards Hadyn --- Outgoing mail is certified Virus Free. Checked by AVG anti-virus system (http://www.grisoft.com). Version: 6.0.521 / Virus Database: 319 - Release Date: 23/09/2003